(a) In order to enforce a claim against a payment bond, a claimant shall give the preliminary notice provided in Chapter 3 (commencing with Section 9300).
(b) If preliminary notice was not given as provided in Chapter 3 (commencing with Section 9300), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
(c) Commencing July 1, 2012, and except as provided in subdivision (b), if the preliminary notice was required to be given by a person who has no direct contractual relationship with the contractor, and who has not given notice as provided in Chapter 3 (commencing with Section 9300), that person may enforce a claim by giving written notice to the surety and the bond principal, as provided in Section 9562, within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
(d) Subdivision (c) shall not apply in either of the following circumstances:
(1) All progress payments, except for those disputed in good faith, have been made to a subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services.
(2) The subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services has been terminated from the project pursuant to the contract, and all progress payments, except those disputed in good faith, have been made as of the termination date.
(e) Pursuant to Section 9300, this section shall not apply to a laborer, as defined under Section 8024.
(f) This section shall become operative on July 1, 2012.
Cite this article: FindLaw.com - California Code, Civil Code - CIV § 9560 - last updated January 01, 2025 | https://codes.findlaw.com/ca/civil-code/civ-sect-9560/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)