A. As a guarantee that the contractor will enter into a contract, bid security is required for all construction procured pursuant to § 41-2533 and all construction services procured pursuant to § 41-2578, subsection F or § 41-2579, subsection F if the purchasing agency estimates that the budget for construction, excluding the cost of any finance services, maintenance services, operations services, design services, preconstruction services or other related services included in the contract, will be more than the amount established by § 41-2535, subsection D. Bid security shall be a certified check or surety bond.
B. Bid security shall be submitted in the following amounts:
1. For design-bid-build construction services, ten percent of the contractor's bid.
2. For design-build construction services awarded by competitive sealed proposals pursuant to § 41-2578, subsection F, ten percent of the purchasing agency's construction budget for the project as stated in the request for proposals, excluding finance services, maintenance services, operations services, design services, preconstruction services or any other related services included in the contract.
3. For job-order-contracting construction services awarded by competitive sealed proposals pursuant to § 41-2578, subsection F or § 41-2579, subsection F, the amount prescribed by the purchasing agency in the request for proposals, but not more than ten percent of the purchasing agency's reasonably estimated budget for construction that the purchasing agency believes is likely to actually be done during the first year under the contract, excluding any finance services, maintenance services, operations services, design services, preconstruction services or other related services included in the contract.
C. This section does not prevent a state governmental unit from requiring such bid security in relation to any construction contract. The surety bond shall be executed and furnished as required by title 34, chapter 2 or chapter 6, 1 as applicable, and the conditions and provisions of the surety bond regarding the surety's obligations shall follow the form required by § 34-201 or 34-608, as applicable.
D. If the invitation for bids or request for proposals requires security, noncompliance requires that the bid be rejected unless, pursuant to rules, it is determined that the bid fails to comply in a nonsubstantial manner with the security requirements.
E. After the bids or proposals are opened, they are irrevocable for the period specified in the invitation for bids or request for proposals, except as provided in § 41-2533, subsection F, § 41-2578, subsection F and § 41-2579, subsection F. If a bidder is permitted to withdraw its bid before award, no action may be had against the bidder or the bid security.
Cite this article: FindLaw.com - Arizona Revised Statutes Title 41. State Government § 41-2573. Bid security - last updated January 01, 2025 | https://codes.findlaw.com/az/title-41-state-government/az-rev-st-sect-41-2573/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)