Learn About The Law
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Current as of January 01, 2025 | Updated by Findlaw Staff
A. The state mine inspector must approve any substantial change to an approved reclamation plan as provided by this section before the change is implemented.
B. The owner or operator of the exploration operation or mining unit shall submit a notice of a proposed change to the inspector describing the purpose and scope of the proposed change and whether it constitutes a substantial change to the approved reclamation plan. If the inspector fails to respond within thirty days, the change is considered to be consistent with the operation's or unit's approved reclamation plan.
C. If the inspector determines that the change is substantial the inspector shall:
1. Notify the owner or operator of the decision within fifteen days after receiving the notice.
2. Require the owner or operator to submit an amendment to the plan for approval. The inspector shall approve or disapprove the amended plan within ninety days after receiving the amended plan.
D. The following changes are not considered to be substantial, and the owner or operator is required to file only an amendment to the reclamation plan and modify the financial assurance as necessary:
1. New surface disturbances that can be reclaimed in a manner that is substantially similar to the manner of reclamation included in the approved plan.
2. Changes in the specific techniques for reclamation, including the equipment used and the mixes of seeds and soils.
3. Changes in location, configuration or acreage of surface disturbances unless the changes substantially affect the reclamation measures stated in the reclamation plan.
E. Before implementing a substantial change in an approved reclamation plan, the owner or operator shall submit to the inspector a revised financial assurance mechanism to account for the substantial change.
F. If a surface disturbance is created on more than fifty acres of land that are not included in an initial reclamation plan, the owner or operator shall submit to the inspector a fee of not more than three dollars for each new acre of surface disturbance. This fee shall be submitted with either the notice of proposed change required in subsection B or with a plan amendment submitted pursuant to subsection D.
Cite this article: FindLaw.com - Arizona Revised Statutes Title 27. Minerals, Oil and Gas § 27-927. Substantial changes to approved reclamation plan; fee - last updated January 01, 2025 | https://codes.findlaw.com/az/title-27-minerals-oil-and-gas/az-rev-st-sect-27-927/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)