West Virginia Code Chapter 24. Public Service Commission § 24-2-19. Integrated Resource Planning Required
Current as of January 01, 2020 | Updated by FindLaw Staff
Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
(a) Not later than March 31, 2015, the Public Service Commission shall issue an order directing any electric utility that does not have an existing requirement approved by the Public Service Commission that provides for the future review of both supply side and demand side resources to develop an initial integrated resource plan to be filed not later than January 1, 2016, in conjunction with other similar deadlines required by other states or entities of the electric utilities. This order may include guidelines for developing an integrated resource plan.
(b)(1) Any electric utility that has an existing requirement approved by the Public Service Commission that provides for the future review of both supply side and demand side resources is exempt from this initial integrated resource plan filing until such time as that existing requirement has been satisfied. Thereafter, such electric utility is required to file an integrated resource plan pursuant to subsection (a) of this section.
(2) Each electric utility that has filed the initial integrated resource plan shall file an updated plan at least every five years after the initial integrated resource plan has been filed. Any electric utility that was exempt from filing an initial integrated resource plan shall file an integrated resource plan within five years of satisfying any existing requirement and at least every five years thereafter. All integrated resource plans shall comply with the provisions of any relevant order of the Public Service Commission establishing guidelines for the format and contents of updated and revised integrated resource plans.
(c) The Public Service Commission shall analyze and review an integrated resource plan. The Public Service Commission may request further information from the utility, as necessary. Nothing in this section affects the obligations of utilities to obtain otherwise applicable commission approvals.
(d) The Commission may consider both supply-side and demand-side resources when developing the requirements for the integrated resource plans. The plan shall compare projected peak demands with current and planned capacity resources in order to develop a portfolio of resources that represents a reasonable balance of cost and risk for the utility and its customers in meeting future demand for the provision of adequate and reliable service to its electric customers as specified by the Public Service Commission.
Cite this article: FindLaw.com - West Virginia Code Chapter 24. Public Service Commission § 24-2-19. Integrated Resource Planning Required - last updated January 01, 2020 | https://codes.findlaw.com/wv/chapter-24-public-service-commission/wv-code-sect-24-2-19.html
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
Was this helpful?