North Carolina General Statutes Chapter 22C. Payments to Subcontractors § 22C-4. Conditions of payment
Current as of January 01, 2020 | Updated by FindLaw Staff
Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Nothing in this Chapter shall prevent the contractor, at the time of application and certification to the owner, from withholding such application and certification to the owner for payment to the subcontractor for: unsatisfactory job progress; defective construction not remedied; disputed work; third party claims filed or reasonable evidence that claim will be filed; failure of subcontractor to make timely payments for labor, equipment, and materials; damage to contractor or another subcontractor; reasonable evidence that subcontract cannot be completed for the unpaid balance of the subcontract sum; or a reasonable amount for retainage not to exceed the initial percentage retained by the owner.
Cite this article: FindLaw.com - North Carolina General Statutes Chapter 22C. Payments to Subcontractors § 22C-4. Conditions of payment - last updated January 01, 2020 | https://codes.findlaw.com/nc/chapter-22c-payments-to-subcontractors/nc-gen-st-sect-22c-4.html
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
Was this helpful?