North Carolina General Statutes Chapter 22C. Payments to Subcontractors § 22C-3. Time of payment to subcontractors after contractor or other subcontractor has been paid

Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.

When a subcontractor has performed in accordance with the provisions of his contract, the contractor shall pay to his subcontractor and each subcontractor shall pay to his subcontractor, within seven days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor's work and materials based on work completed or service provided under the subcontract.

Cite this article: FindLaw.com - North Carolina General Statutes Chapter 22C. Payments to Subcontractors § 22C-3. Time of payment to subcontractors after contractor or other subcontractor has been paid - last updated January 01, 2020 | https://codes.findlaw.com/nc/chapter-22c-payments-to-subcontractors/nc-gen-st-sect-22c-3.html


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.