Sec. 11. (a) As used in this section, “legacy generation resource” means an electric generating facility owned directly or indirectly by a corporation that was formed for the original purpose of providing power to the federal government for use in the nation's defense or in furtherance of national interests, including the Ohio Valley Electric Corporation.

(b) As used in this section, “reliable capacity resource” means an electric generating unit:

(1) that is located in Indiana;

(2) the capacity of which is valued by a regional transmission organization at a minimum of eighty percent (80%) of the unit's nameplate capacity;  and

(3) that maintains an annual average onsite fuel inventory of at least thirty (30) days of average fuel consumption.

(c) The general assembly finds that it is in the public interest to support the reliability, availability, fuel security, and diversity of electric generating capacity in Indiana for the purpose of providing reliable and stable electric service to customers of public utilities.

(d) A public utility that owns and operates a reliable capacity resource shall operate and maintain the unit using good utility practices and in a manner reasonably intended to support the availability of the unit for dispatch and for providing reliable service to customers of the public utility.

(e) A public utility may not terminate a power agreement with a legacy generation resource in which the public utility has an ownership interest unless the public utility provides the commission with at least three (3) years advance notice of the termination.  The commission shall determine the reasonable costs incurred by the public utility under the power agreement and allow the public utility to recover those costs in a fuel adjustment charge proceeding under IC 8-1-2-42.  For purposes of this subsection, a public utility's reasonable costs related to a legacy generation resource means those costs, including deferred costs, allocated under a power agreement approved by the Federal Energy Regulatory Commission and relating to a legacy generation resource.

(f) A public utility may not retire, sell, or transfer a reliable capacity resource with a capacity exceeding eighty (80) megawatts before May 1, 2021, unless:

(1) the public utility first provides written notice to the commission of the public utility's intent to do so;  and

(2) the commission conducts a public hearing, noticed in accordance with IC 5-14-1.5, to receive information concerning the reasonableness of the planned retirement, sale, or transfer.

A public utility may provide the written notice required under subdivision (1) at any time.  Not later than one hundred twenty (120) days after the date of the commission's receipt of the public utility's written notice to the commission under this subsection, the commission shall conduct the hearing described in subdivision (2) and issue the commission's analysis and conclusions concerning the reasonableness of the planned retirement, sale, or transfer based on the information received.  If the planned retirement, sale, or transfer was included in the public utility's preferred portfolio in the public utility's most recent integrated resource plan, the public utility may proceed with the planned retirement, sale, or transfer after the commission issues the commission's analysis and conclusions under this subsection.  If the planned retirement, sale, or transfer was not included in the public utility's preferred portfolio in the public utility's most recent integrated resource plan, the public utility may not proceed with the planned retirement, sale, or transfer until at least six (6) months have elapsed from the date of the commission's receipt of the public utility's written notice under this subsection.

(g) If a public utility that seeks to retire, sell, or transfer a reliable capacity resource under subsection (f) cites a federal mandate as the basis, in whole or in part, for the planned retirement, sale, or transfer of the unit, the commission may consider as part of the commission's analysis and conclusions under subsection (f) whether the cited federal mandate:

(1) is in force;

(2) has not expired or been revoked;  and

(3) is not merely anticipated to be enacted;

at the time of the public utility's notice under subsection (f).

(h) This section expires May 1, 2021.

Cite this article: FindLaw.com - Indiana Code Title 8. Utilities and Transportation § 8-1-8.5-11 - last updated June 08, 2021 | https://codes.findlaw.com/in/title-8-utilities-and-transportation/in-code-sect-8-1-8-5-11.html


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.

Was this helpful?

Thank you. Your response has been sent.

Copied to clipboard