(a) An analysis of the data provided under § 300.11 must be supported by an appropriate methodology developed by the Administrator.
(b) Revenue recovery study.
(1) A study must be provided which supports the filed rate and charges, including a narrative statement that explains how the rates and charges meet the objective of recovering the revenue necessary to repay the Federal investment and other costs in a reasonable period of time.
(2) Any Power Repayment Study (PRS) submitted for this purpose must be developed using currently approved rates for estimating future revenues. If the filed rates differ from the current rates, the Administrator must provide a PRS which uses the level of revenues produced by the proposed rates. Unless otherwise required by statute, a PRS must contain only those investments in plant which will be in commercial operation during the proposed rate approval period, except replacements. Forecasts of costs beyond the rate test period must be based on conditions prevailing during the period, unless unusual circumstances warrant otherwise.
(3) A PRS must include, but need not be limited to, those items listed below:
(i) Operating revenues;
(ii) Operating expenses;
(iii) Interest expense;
(iv) Investment placed in service (using totals if the supporting statement annually shows a breakdown into the appropriate subcategories under each major heading), including the initial project, additions, replacements, and the total investment;
(v) Investment amortized;
(vi) Remaining unamortized investment;
(vii) Allowable unamortized investment (using totals if the supporting statement annually shows a breakdown into the appropriate subcategories under each major heading), including initial project, additions, replacements, and total investment;
(viii) Irrigation investment assigned to be repaid from power revenues (using totals if the supporting statement annually shows a breakdown into the appropriate subcategories under each major heading), including irrigation investment assigned to power, investment repaid, remaining unpaid investment, and allowable unpaid investment; and
(ix) Cumulative status of repayment.
(c) Cost of service study. For any project or system which provides more than one class of service for which differing rates are proposed, a cost of service study, if available, must be provided which shows how the costs of providing each service have been determined. If rates and charges have not been formulated on a cost related basis, the basis for each rate or charge should be explained.
Cite this article: FindLaw.com - Code of Federal Regulations Title 18. Conservation of Power and Water Resources § 18.300.12 Analysis of supporting data - last updated October 02, 2022 | https://codes.findlaw.com/cfr/title-18-conservation-of-power-and-water-resources/cfr-sect-18-300-12.html
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
Response sent, thank you
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)