California Code, Public Contract Code - PCC § 20869

Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.

When the certificate of completion has been recorded the contractor shall be entitled to payment for the full amount of the contract price, and the recording of the certificate shall be sufficient notice to the owner of such track or tracks that such amount is due and payable.

Cite this article: FindLaw.com - California Code, Public Contract Code - PCC § 20869 - last updated January 01, 2019 | https://codes.findlaw.com/ca/public-contract-code/pcc-sect-20869.html


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.

Was this helpful?

Thank you. Your response has been sent.

Copied to clipboard