Alabama Code Title 6. Civil Practice § 6-5-703

Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.

If, prior to or during the course of construction, a contractor discovers or determines that following the plans and specifications could result in a potentially dangerous condition, then the contractor shall, with specificity of such condition, expressly notify the Chief Engineer of the Alabama Department of Transportation in writing by certified mail, return receipt requested. The Alabama Department of Transportation, or the awarding authority, shall respond to the specific condition raised within 14 days in writing as to its decision as to the appropriate response to the dangerous condition. The contractor shall not be liable for any claim relating to any decision made by the Alabama Department of Transportation or awarding authority as to the appropriate response, design decisions, or engineering decision, if any, to respond to the potentially dangerous condition identified.

Cite this article: FindLaw.com - Alabama Code Title 6. Civil Practice § 6-5-703 - last updated December 30, 2022 | https://codes.findlaw.com/al/title-6-civil-practice/al-code-sect-6-5-703/


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.

Was this helpful?

Thank you. Your response has been sent.

Copied to clipboard