Texas Property Code - PROP § 53.103. Lien on Retained Funds




A claimant has a lien on the retained funds if the claimant:

(1) sends the notices required by this chapter in the time and manner required;  and

(2) except as allowed by Section 53.057(f) , files an affidavit claiming a lien not later than the 30th day after the earliest of the date:

(A) the work is completed;

(B) the original contract is terminated;  or

(C) the original contractor abandons performance under the original contract.